Choudhary Brothers hardware vendor left you voicemail saying that a snowstorm in the Midwest will prevent your equipment from arriving on time. You identified a risk response for this risk and have arranged for a local company to lease you the needed equipment until yours arrives. This is an example of which risk response strategy?
This multiple choice question (MCQ) is related to the book/course
vu cs615 Software Project Management.
It can also be found in
vu cs615 Final Term - Quiz No.18.
Choudhary Brothers hardware vendor left you voicemail saying that a snowstorm in the Midwest will prevent your equipment from arriving on time. You identified a risk response for this risk and have arranged for a local company to lease you the needed equipment until yours arrives. This is an example of which risk response strategy?
Transference
Acceptance
Mitigation
Avoidance