If for path 1-3-4 time is 5 3 8 days for path 1-2-3-4 time is 6-18745
If for path 1-3-4 time is 5+3 = 8 days, for path 1-2-3-4 time is 6+7+3 = 16 days and for path 1-2-4 time is 6+6 = 12 days, then which of the followings is true.
This multiple choice question (MCQ) is related to the book/course vu mth601 Operations Research. It can also be found in vu mth601 Final Term - Quiz No.3.
If for path 1-3-4 time is 5+3 = 8 days, for path 1-2-3-4 time is 6+7+3 = 16 days and for path 1-2-4 time is 6+6 = 12 days, then which of the followings is true.
1-3-4 is critical path
1-2-4 is critical path
1-2-3-4 is critical path
1-4 is critical path