In a network flow diagram, for an activity (i, j) of duration of three days, if its earliest start time is of two days then which of the following will be its early finish time?
This multiple choice question (MCQ) is related to the book/course vu mth601 Operations Research. It can also be found in vu mth601 Final Term - Quiz No.3.
In a network flow diagram, for an activity (i, j) of duration of three days, if its earliest start time is of two days then which of the following will be its early finish time?
Six days
One day
One and half day
Fifth days