In the phase of Early Start and Early Finish to find the-18724

In the phase of Early Start and Early Finish, to find the Critical Path in a network flow diagram, for the first node (event), we start with time __________.

Online Quiz This multiple choice question (MCQ) is related to the book/course vu mth601 Operations Research. It can also be found in vu mth601 Final Term - Quiz No.1.