In a development project, if an activity (i, j) of duration three days finish earlier on the tenth day then which of the following will be its earler start day?
This multiple choice question (MCQ) is related to the book/course vu mth601 Operations Research. It can also be found in vu mth601 Final Term - Quiz No.1.
In a development project, if an activity (i, j) of duration three days finish earlier on the tenth day then which of the following will be its earler start day?
Seventh day
Third day
First day
Fifth day