Feedback for subjective question
Question 1:
Following costs were added during the process.
Required:
You are required to calculate equivalent units of material, labour and factory overhead and unit cost of material, labour and factory overhead.
| Units transferred to next department | 40,000 |
| Units still in process (all material, 2/3 labour & FO H) | 8,000 |
| Abnormal loss (1/2 complete as to material, Labour and FOH) | 1,000 |
| Materials | Rs.40,500 |
| Labour | 101,700 |
| Factory overhead | 50,500 |
You are required to calculate equivalent units of material, labour and factory overhead and unit cost of material, labour and factory overhead.
Current Answer: