Pervaiz Elahi is a project manager for Changing Tides Video games. He has gathered the inputs of for the Activity Duration Estimation process. He will employ which tools and techniques to produce the outputs for this process?
This multiple choice question (MCQ) is related to the book/course vu cs615 Software Project Management. It can also be found in vu cs615 Final Term - Quiz No.16.
Pervaiz Elahi is a project manager for Changing Tides Video games. He has gathered the inputs of for the Activity Duration Estimation process. He will employ which tools and techniques to produce the outputs for this process?
Activity list, analogous estimating, quality based durations, and alternatives identification
Activity list, analogous estimating, expert judgment, and quality based durations
Expert judgment, analogous estimating, quality based durations, and reserve time
Expert judgment, alternative identification, quality based durations, and reserve time