COMSAT project selection committee used a weighted scoring-08673
COMSAT project selection committee used a weighted scoring model and found that project BAT, with a score of 54, should be chosen over the other competing projects. Which of the following is true?
This multiple choice question (MCQ) is related to the book/course vu cs615 Software Project Management. It can also be found in vu cs615 Final Term - Quiz No.14.
COMSAT project selection committee used a weighted scoring model and found that project BAT, with a score of 54, should be chosen over the other competing projects. Which of the following is true?
Weighted scoring models are a benefit measurement method, which is tool and technique in the Initiation process
Weighted scoring models are constraint optimization method, which is output of the Initiation process
Weighted scoring models are constraint optimization method, which is tool and technique in the Initiation process
Weighted scoring models are a benefit measurement method, which is output of the Initiation process