Which of the following Technique use network schedules to trace-08640
Which of the following Technique use network schedules to trace the completion of predetermined activities?
This multiple choice question (MCQ) is related to the book/course
vu cs615 Software Project Management.
It can also be found in
vu cs615 Final Term - Quiz No.10.
Which of the following Technique use network schedules to trace the completion of predetermined activities?
Gantt Charts
PERT
CPM
PERT and CPM