Which of the following Technique use network schedules to trace-08640

Which of the following Technique use network schedules to trace the completion of predetermined activities?

Online Quiz This multiple choice question (MCQ) is related to the book/course vu cs615 Software Project Management. It can also be found in vu cs615 Final Term - Quiz No.10.