In order to use the PERT and CPM which one of the following is-07936
In order to use the PERT and CPM, which one of the following is NOT required?
This multiple choice question (MCQ) is related to the book/course vu cs605 Software EngineeringII. It can also be found in vu cs605 Final Term - Quiz No.3.
In order to use the PERT and CPM, which one of the following is NOT required?
Decomposition of tasks - also known as the work breakdown structure (WBS).
Teams communication mode details.
Estimation of effort.
Interdependencies.