Critical path defines-07920
Critical path defines:
This multiple choice question (MCQ) is related to the book/course
vu cs605 Software EngineeringII.
It can also be found in
vu cs605 Final Term - Quiz No.1.
Critical path defines:
The list of the resources that may be needed for future activities.
The chain of tasks that determines the duration of the project.
The list of the deficient resources, project is suffering from.
None of the given