Which of the following phases are performed to find the-18742
Which of the following phases are performed to find the critical path in CPM?
This multiple choice question (MCQ) is related to the book/course
vu mth601 Operations Research.
It can also be found in
vu mth601 Final Term - Quiz No.3.
Which of the following phases are performed to find the critical path in CPM?
Forward and Backward (Early and Late finish program)
Program Evaluation and Review
Resource Scheduling and Allocation
Precedence and succession